Retaining wall

240 t tank base raft fixed over 5 weeks, water treatment, North West England.

  • Water treatment
  • North West England
  • 5 weeks on site, as-built
  • 240 treinforcement fixed, as-built
  • 5weeks on site, start to sign-off
  • Raftelement: tank base raft
  • NWNorth West England, water treatment

What we
fixed

A tank base raft on a water treatment site, fixed as a single package from setting out to sign-off.

The raft was fixed as a double mat: bottom steel laid, spaced and tied first, then chairs and top steel worked off the same setting-out lines. Bar marks came off the client’s schedules and were checked against the drawing before each section was closed out.

Cover was held on proprietary spacers and chairs to the values on the engineer’s drawing. Laps were positioned to the schedule rather than the gang’s convenience, and starter bars for the tank wall were set and tied off before the pour so nothing had to be moved later.

Access was sequenced with the groundworker so the gang worked away from the concrete gang, and the raft was handed over as complete sections rather than one inspection at the end.

Element
Ground beams
Tonnage
17 t
Programme
2 weeks
Sector
Industrial
Location
East of England

How it ran

Four stages, worked back from the pour dates on the contractor’s programme.

  1. Week 1

    Setting out and bottom steel

    Schedules checked against the drawing, setting-out lines agreed with the site engineer, bottom mat laid and spaced.

  2. Weeks 2–3

    Chairs and top steel

    Chairs set to hold cover, top mat tied out section by section, laps positioned to the schedule.

  3. Week 4

    Wall starters

    Tank wall starters set and tied off in position, so the wall gang inherited steel that did not need adjusting.

  4. Week 5

    Inspection and pour

    Sections walked with the engineer, snags closed the same day, raft released for the pour on the programme date.

Raft steel complete, on spacers, ahead of the engineer’s walk.
Raft steel complete, on spacers, ahead of the engineer’s walk.

Scope and standards

What was in our package, and what it was worked to. Anything not listed sat with another trade.

Package type
Labour supply against the client’s steel
In scope
Bottom mat, chairs, top mat, wall starters, tying and spacing
Not in scope
Groundworks, formwork, concrete, steel supply
Tonnage fixed
240 t
Weeks on site
5
Reinforcing steel
BS 4449, grades B500B and B500C
Bar shapes and scheduling
BS 8666, to the client’s bar schedules
Documentation
RAMS issued before start; cards submitted with the package

Cover, lap and centre values are design values from the engineer’s drawings and are not published here. Client name withheld until we have sign-off to publish it.

Next on
the record

Retaining wall starters on a highways scheme, fixed to the formwork cycle. The full record lists element, tonnage, programme, sector and region for every package.

CIS registered£1m public liability£10m employers’ liabilityRAMS before we start

Need
steel
fixers
on site?

Send the drawings and bar bending schedules.
We come back with a price or a labour rate.